Suggested workplan with deadlines

Below I suggest a work plan with deadlines, separated in the protocol phase, the execution and the reporting phase (note that there is an overlap between execution and reporting). All of this is how I would organise the work and it is not how you have to work. All deadlines (but the peer-review ones) are to be understood as “soft”. Decide on the exact steps and deadlines within your group. I will regularly send emails with suggested steps and reminders.

Phase 1 – Get protocol logged (14 Oct – 11 Nov)

Deadline Task Done when …
Wed 14 Oct (in session) We will set up the GitLab repository (fork from template); move the protocol draft into the Quarto protocol; update README (incl. link to the original paper) and folder structure if needed Repo exists; instructors and paired group have access
Wed 21 Oct Lock protocol v1: finalise the protocol and create a tagged commit protocol-v1. Open a GitLab issue assigning the peers that were paired to review your protocol, linking to the tagged commit / protocol Tag protocol-v1 visible; review issue open
Wed 28 Oct Peer review (round 1): give written feedback on an other group’s protocol via GitLab issue(s). Are the claims to be reproduced unambiguous? Are the analytic steps specific enough to follow? Are the anticipated deviations plausible and complete? Feedback posted on the other group’s repository
Fri 30 Oct or Mon 9 Nov Optional: Consultation by me before final lock – request via GitLab issue (tag rachel.heyard@uzh.ch) or email. I will be away 2–6 Nov. Request sent (if wanted)
Wed 11 Nov Final lock: implement feedback, reply to review comment and close the issues; create tagged commit protocol-final. Groups not needing a consultation are encouraged to lock earlier and start executing. Tag protocol-final exists; all review issues answered and closed

Phase 2 – Execution (from protocol lock – 1 Dec)

Deadline Task Done when …
After lock Execute the reproduction. Log every deviation or ambiguity as it occurs: what the protocol said, what you did instead, why, and whether it was forced by missing information or is an interpretive choice. Commit log entries together with the work they describe –
Wed 18 Nov (in session) After the guest lecture, short status report per group (~3 min): protocol locked? Does the code run? What’s broken? –
Tue 24 Nov Repository in reviewable state: README current, any deviation recorded, code and outputs committed Last commit before session
Wed 25 Nov (in session) Peer review (round 2), possibly with a different group than in round 1: +/- 30 min, written feedback via GitLab issue on readability (could someone else follow the structure?), traceability (is it clear what was done and why?), and deviations (any undocumented ones? are documented ones justified?) Issue posted on the other group’s repo
Tue 1 Dec Execution complete: actionable round-2 feedback incorporated; results presentation prepared Final results committed

Phase 3 – Reporting (18 Nov – 9 Dec)

Deadline Task Done when …
From 18 Nov Start the Standardized Reproduction Template (StaRT). Copy the sections that mirror your protocol (paper details, claims, planned steps) early, so only results and discussion remain Report skeleton in repo
Wed 2 Dec (in session) Present your reproduction outcome: did the code, run as specified, produce the reported results? Walk through the deviation log – forced by missing information vs. interpretive choices Presentation given
Wed 9 Dec Finalise the StaRT report and create tagged commit report-v1. In session: input on innovations in publishing, discussion of common learnings, plan for manuscript finalisation and submission to Replication Research Tag report-v1 exists